Question: Given the project activity information provided below: a) Draw the project network. b) What is the critical path? Activity (ID) Description 1 2 3 4

 Given the project activity information provided below: a) Draw the project

Given the project activity information provided below: a) Draw the project network. b) What is the critical path? Activity (ID) Description 1 2 3 4 5 6 7 8 9 10 11 Requirements Architecture Design C Design S Design M Coding U Coding T Coding N Integration I Integration ) System Preceding Activity None 1 2 2 2 3 4,5 5 6,7 7,8 9,10 Activity Time (DUR) (days) 30 30 16 15 5 8 8 6 5 4 10