Question: Given the project activity table below: Activity Duration ( weeks ) Dependency A 8 B 4 C 3 D 3 A E 1 C F
Given the project activity table below:Activity Durationweeks DependencyA B C D AE CF CG DH BDEI EFJ HK GI,Ja Draw a project network from the table above marksbi What activitys is a burst activity? markii What activitys is a merge activity? markiii What is the length of the project? markiv What is the critical path? markc Draw the Gantt chart marksd Build the project network using expected activity times based on the new table below markse What would be the expected length of the project? markf What would be the project standard deviation? marksg Using a ztable one can be found here: https:statisticsbyjimcomhypothesistestingztable whatis the probability that the project can be completed in weeks? marks