Question: Given the project information below, answer the following questions: Most Expected Variance Activity Predecessor Optimistic Likely Pessimistic Time (Te) Time (a) Time Time (b) (m)

Given the project information below, answer the

Given the project information below, answer the following questions: Most Expected Variance Activity Predecessor Optimistic Likely Pessimistic Time (Te) Time (a) Time Time (b) (m) A None 3 12 27 B None 8 20 26 A 4 7 16 D A, B 27 30 45 E C,D 10 13 16 Question C7Q1: Using PERT method and based on expected time (Te) for each activity, determine the expected project duration (rounded to whole numbers)