Question: Given the project information below, develop an AON project network and answer the questions that follow: Activity ID Duration ( in days ) Predecessor A

Given the project information below, develop an AON project network and answer the
questions that follow:
Activity ID Duration (in days) Predecessor
A 5-
B 4 A
C 5 A
D 6 B
E 3 C
F 4 D, E
1.1. Complete the forward and backward pass. [13]