Question: Given the project network for: Activity EST EFT LST LFT A 0 2 0 2 B 2 3 3 4 C 2 4 2 4
Given the project network for: Activity EST EFT LST LFT A 0 2 0 2 B 2 3 3 4 C 2 4 2 4 D 4 7 4 7 Which of the following is a slack time formula for activity B? 4 3 4 2 2 3 3 3