Question: Given the project network for: Activity EST EFT LST LFT A 0 2 0 2 B 2 3 3 4 C 2 4 2 4
Given the project network for: Activity EST EFT LST LFT A 0 2 0 2 B 2 3 3 4 C 2 4 2 4 D 4 7 4 7 The completion time for this project is __________ weeks. 2 + 4 + 4 + 7 2 + 2 + 3 0 + 2 + 4 8