Question: Given the project network provided in the attachment, what task or tasks would you crash to reduce the project by one day? What is the
Given the project network provided in the attachment, what task or tasks would you crash to reduce the project by one day? What is the cost of the project after you crash the cost by one day? What is the new duration? Please include your excel file with all calculations.
| Normal | Crash | Crash Cost Per Day | ||||
| Task | Pred | Duration | Cost | Duration | Cost | |
| a | - | 5 | $ 500 | 5 | $ 500 | |
| b | a | 10 | $ 2,000 | 8 | $ 2,400 | |
| c | a | 5 | $ 1,500 | 3 | $ 4,500 | |
| d | b | 15 | $ 1,500 | 14 | $ 2,000 | |
| e | c | 30 | $ 4,500 | 25 | $ 15,000 | |
| f | d, e | 5 | $ 500 | 5 | $ 500 | |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
