Question: Given the project network provided in the attachment, what task or tasks would you crash to reduce the project by one day? What is the

Given the project network provided in the attachment, what task or tasks would you crash to reduce the project by one day? What is the cost of the project after you crash the cost by one day? What is the new duration? Please include your excel file with all calculations.

Normal Crash Crash Cost Per Day
Task Pred Duration Cost Duration Cost
a - 5 $ 500 5 $ 500
b a 10 $ 2,000 8 $ 2,400
c a 5 $ 1,500 3 $ 4,500
d b 15 $ 1,500 14 $ 2,000
e c 30 $ 4,500 25 $ 15,000
f d, e 5 $ 500 5 $ 500