Question: Given the project network shown below, the earliest finish time for activity e is: A precedence network with 7 nodes.In the precedence network the start

Given the project network shown below, the earliest finish time for activity e is:
A precedence network with 7 nodes.In the precedence network the start node is a and the end node is g. The paths in the network are as follow:a-b-e-g;a-b-d-e-g; a-b-d-f-g; a-c-d-f-g; a-c-d-e-g; The time associated with each node is as follows: a,4; b,5; c,7; d.2; e,3; f.3; and g.6.
Multiple Choice
13
16
22
11
24