Question: Given the project network shown below, the earliest finish time for activity e is: A precedence network with 7 nodes.In the precedence network the start
Given the project network shown below, the earliest finish time for activity e is:
A precedence network with nodes.In the precedence network the start node is a and the end node is g The paths in the network are as follow:abeg;abdeg; abdfg; acdfg; acdeg; The time associated with each node is as follows: a; b; c; d; e; f; and g