Question: Given the project network shown below, the earliest finish time for activity e is: A precedence network with 7 nodes. Question 3 Answer a .

Given the project network shown below, the earliest finish time for activity e is:
A precedence network with 7 nodes.
Question 3Answer
a.
13
b.
22
c.
11
d.
16
e.
24