Question: Given the project table below, what is the crash cost for 8 hours of time-savings? Enter a rounded whole dollar amount with dollar sign; use

Given the project table below, what is the crash
Given the project table below, what is the crash cost for 8 hours of time-savings? Enter a rounded whole dollar amount with dollar sign; use commas if necessary. Normal Crash Crash Activity Immediate Predecessor(s) Normal Time (hours) Cost ($) Time (hours) Cost (5) A 2. 10 2. 0 B A 3 15 2. 23 00 un 25 4 30 C 3 20 1 1 24 E 30 4 45 F CE 1 5 1 0 G F 7 35 6 50 H D.G 10 50 7 62