Question: Given the project table below, what is the crash cost for 8 hours of time-savings? Enter a rounded whole dollar amount with dollar sign; use

Given the project table below, what is the crash
Given the project table below, what is the crash cost for 8 hours of time-savings? Enter a rounded whole dollar amount with dollar sign; use commas if necessary. Normal Normal Crash Crash Immediate Activity Time (hours) Cost ($) Time (hours) Cost ($) Predecessor(s) A 2. . 10 2 0 None B 3 15 2 23 A 5 25 4 30 A D 3 20 1 24 E 6 30 4. 45 C F 1 5 1 o BE G 7 35 6 50 EF H 10 40 7 52 D.G