Question: Given the project within the table below, calculate the following: Activity Duration ( hours ) Immediate Predecessors A 4 none B 9 A C 8
Given the project within the table below, calculate the following:
Activity Duration hours Immediate Predecessors
A none
B A
C A B
D C
E none
F D E
G F
a What is the project length?
Select
b What activities are on the critical path?
Select
c How much slack is in activity B
Select
d What is the Late Start Late Finish for activity E
Select
f What if activity E was delayed by hours now taking hours what impact would it have on the overall project?
Select
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
