Question: Given the project within the table below, calculate the following: Activity Duration ( hours ) Immediate Predecessors A 4 none B 9 A C 8

Given the project within the table below, calculate the following:
Activity Duration (hours) Immediate Predecessors
A 4 none
B 9 A
C 8 A, B
D 7 C
E 2 none
F 3 D, E
G 7 F
a. What is the project length?
[ Select ]
b. What activities are on the critical path?
[ Select ]
c. How much slack is in activity B?
[ Select ]
d. What is the Late Start / Late Finish for activity E?
[ Select ]
f. What if activity E was delayed by 8 hours (now taking 10 hours), what impact would it have on the overall project?
[ Select ]