Question: Given the project within the table below, calculate the following: Activity Duration ( hours ) Immediate Predecessors A 4 None B 8 None C 6
Given the project within the table below, calculate the following:
Activity
Duration hours
Immediate Predecessors
A
None
B
None
C
A
D
B C
E
D
F
E
G
E F
H
G
a What is the project's minimum completion time? Select
b What is the critical path in the project? Select B C D E F GC D E F GB D E F G HA C D E F G HA C D E G H
c What is the slack for activity B Select it is on the critical path",
d What is the Early Start and Early Finish for Activity D Select
e What is the Late Start and Late Finish for activity B Select and and and and and
f What would happen to the overall project length if activity B now took an additional hours to complete, now taking a total of hours? Select the project time would be reduced by hours because activity B is on the critical path. The project would now be hours", "the project length would remain the same, because B is a noncritical activity", "the project length would decrease because activity B has hours worth of slack", "The project would increase by hour, because B has a slack of hours the project is now going to take hours"
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock