Question: Given the project within the table below, calculate the following: Activity Duration (hours) Immediate Predecessors A 4 B 3 C 10 D 7 B,C E

Given the project within the table below,

Given the project within the table below, calculate the following: Activity Duration (hours) Immediate Predecessors A 4 B 3 C 10 D 7 B,C E 1 D IF 1 E 5 A,F a. What is the critical path (Select] and it's length (Select] b. How much slack does activity A have? (Select) c. How much slack does activity B have? (Select] d. How much slack does activity G have? (Select] e. For activity E, what is the late start (Select] , and the late finis [Select]