Question: Given the same network as discussed in the lecture: activities.png Recall that the critical path is 2 - 5 - 8 - 1 1 and
Given the same network as discussed in the lecture:
activities.png
Recall that the critical path is and their variances are and respectively. Thus, the project completion time along the critical path is normally distributed with mean weeks and standard deviation weeks.
What is the project's expected completion time?
Group of answer choices
weeks
weeks
weeks
weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
