Question: Given the same network as discussed in the lecture: activities.png Recall that the critical path is 2 - 5 - 8 - 1 1 and

Given the same network as discussed in the lecture:
activities.png
Recall that the critical path is 2-5-8-11 and their variances are 1,1/9,16/9, and 4, respectively. Thus, the project completion time along the critical path is normally distributed with mean 25 weeks and standard deviation 2.63 weeks.
What is the project's expected completion time?
Group of answer choices
27 weeks
22 weeks
41 weeks
25 weeks