Question: Given the scenario below, answer questions 4 8 through 5 2 . You are the project manager of a condominium construction project. The proposed building
Given the scenario below, answer questions through
You are the project manager of a condominium construction project. The proposed building is storeys
tall and you plan to construct at a uniform rate of storey per month. The project is expected to cost
$ For the first months work went as planned, but then a key piece of machinery broke and
slowed your pace to storey every months. At the end of month the project has spent
$
What is the CPI of the project?
a
b
c
d
What is the SPI of the project?
a
b
c
d
What is the TSPI of the project?
a
b
c
d