Question: Part 6 : Earned Value Analysis 1 Given the scenario below, answer questions 4 8 through 5 2 . You are the project manager of

Part 6: Earned Value Analysis 1
Given the scenario below, answer questions 48 through 52.
You are the project manager of a condominium construction project. The proposed building is 20 storeys tall and you plan to construct at a uniform rate of 1 storey per month. The project is expected to cost $18,400,000. For the first 9 months work went as planned, but then a key piece of machinery broke and slowed your pace to 1 storey every 1.5 months. At the end of month 12, the project has spent $10,120,000.
48. What is the CPI of the project?
a.0.92
b.0.85
c.1.09
d.1
49. What is the SPI of the project?
a.1
b.0.92
c.1.09
d.0.67
50. What is the TSPI of the project?
a.1.2
b.1
c.0.89
d.1.125
51. You have discovered that you will not be able to fix the piece of machinery before the project completes, and you have re-estimated that the remaining storeys will now cost a total of $10,000,000 to complete. What is your EAC?
a. $20,120,000
b. $21,040,000
c. $20,040,000
d. $19,120,000
52. If your estimate from question 51 was correct, what would your CPI be at the end of the project?
a.1
b.0.91
c.1.09
d.0.89
 Part 6: Earned Value Analysis 1 Given the scenario below, answer

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!