Question: Part 6 : Earned Value Analysis 1 Given the scenario below, answer questions 4 8 through 5 2 . You are the project manager of
Part : Earned Value Analysis
Given the scenario below, answer questions through
You are the project manager of a condominium construction project. The proposed building is storeys tall and you plan to construct at a uniform rate of storey per month. The project is expected to cost $ For the first months work went as planned, but then a key piece of machinery broke and slowed your pace to storey every months. At the end of month the project has spent $
What is the CPI of the project?
a
b
c
d
What is the SPI of the project?
a
b
c
d
What is the TSPI of the project?
a
b
c
d
You have discovered that you will not be able to fix the piece of machinery before the project completes, and you have reestimated that the remaining storeys will now cost a total of $ to complete. What is your EAC?
a $
b $
c $
d $
If your estimate from question was correct, what would your CPI be at the end of the project?
a
b
c
d
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
