Question: Given the table below, assuming that there are only 12 resources available at any time: Activity Dependency Duration Resources A 8 3 B A 2
Given the table below, assuming that there are only 12 resources available at any time:
| Activity | Dependency | Duration | Resources |
| A |
| 8 | 3 |
| B | A | 2 | 4 |
| C | A | 3 | 7 |
| D | B | 4 | 6 |
| E | B,C | 4 | 4 |
| F | C | 2 | 3 |
| G | D | 2 | 7 |
| H | E | 2 | 4 |
| I | F | 1 | 2 |
| J | G,H,I | 1 | 4 |
| K | H,I | 6 | 2 |
| L | J,K | 3 | 6 |
Provide the network diagram
Provide the steps and process to level the schedule based on resource availability
Provide the final Gantt chart. What is the final project duration?