Question: Given the table below, assuming that there are only 12 resources available at any time: Activity Dependency Duration Resources A 8 3 B A 2

Given the table below, assuming that there are only 12 resources available at any time:

Activity

Dependency

Duration

Resources

A

8

3

B

A

2

4

C

A

3

7

D

B

4

6

E

B,C

4

4

F

C

2

3

G

D

2

7

H

E

2

4

I

F

1

2

J

G,H,I

1

4

K

H,I

6

2

L

J,K

3

6

Provide the network diagram

Provide the steps and process to level the schedule based on resource availability

Provide the final Gantt chart. What is the final project duration?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!