Question: Textbook Question 6 A / 3 - 2 Given the table below, assuming that there are only 8 resources available at any time: a )

Textbook Question 6A/3-2
Given the table below, assuming that there are only 8 resources available at any time:
a) Provide the network diagram
b) Provide the original Gantt chart with all resources
c) Provide the steps and process to update the schedule based on resource constraints
d) Provide the final Gant chart (you do not have to recalculate the slack)
e) What is the final project duration?