Question: Textbook Question 6 A / 3 - 2 Given the table below, assuming that there are only 8 resources available at any time: a )
Textbook Question A
Given the table below, assuming that there are only resources available at any time:
a Provide the network diagram
b Provide the original Gantt chart with all resources
c Provide the steps and process to update the schedule based on resource constraints
d Provide the final Gant chart you do not have to recalculate the slack
e What is the final project duration?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
