Question: Given the table below, Calculate the expected duration for the path a-c-e-g-h. Select one: 12 weeks 13 weeks 11 weeks 15 weeks 14 weeks 2.
- Given the table below,

Calculate the expected duration for the path a-c-e-g-h.
Select one:
- 12 weeks
- 13 weeks
- 11 weeks
- 15 weeks
- 14 weeks
2. GD is a home improvement and building supply chain, is going to build a new warehouse facility to serve its stores in three North Cyprus cities Nicosia, Famagusta and Lefka. The coordinates of these cities (in miles), using Kyrenia, Northern Region as the graphical region (0,0) and the annual truckload trips that supply each store are as follows:

Calculate the X coordinate for the facility location.
Select one:
- 74.07
- 78.12
- 80.25
- 76.87
- 72.06
3. The following table contains information related to the major activities of a research project. Use the information to do a dummy activity.

Calculate the early start time for activity C.
Select one:
- 8
- 10
- 2
- 1
- 0
PLZ ANSWER ALL 3 QUESTIONS
I WILL GIVE YOU ALL THE SUPPORT THAT IS A PROMISE.
Activity Time(weeks) Immediate Predecessor A 7-23 B 234 1-2-3 D A B, dummy 2-4-6 E 1-4-7 F 1-2-9 G DE 3-4-11 H F.G 1-2-3 END H Coordinates Store Y Truckload Shipment Nicosia 18 85 160 Famagusta 125 140 Lefka 180 20 25 Activity Immediate Predecessor Expected Timedays A 2 B A 4 c A 5 D B 2 E F B. dummy DE H F F BH 7 Finn
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts