Question: Given the table below, identify the appropriate risk matrix for this project. Event Cost ($000) Probability 1. Equipment breakdown 40 .20 2. Vendor is late
Given the table below, identify the appropriate risk matrix for this project.
| Event | Cost ($000) | Probability | |||
| 1. Equipment breakdown | 40 | .20 | |||
| 2. Vendor is late with key segment | 200 | .60 | |||
| 3. Subcontractor has labor issues | 140 | .30 | |||
| 4. Weather problems | 15 | Unknown | |||
| 5. Funding delays | 50 | .40 to .60 | |||
| 6. Testing delays | 20 | .40 | |||
Click here for the Excel Data File
Multiple Choice
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
