Question: Create a risk matrix for this project: Explain your reasoning for your placement of the events Weather problems and Fundingdelays. Event Cost ($000) Probability Equipment
.png)
Explain your reasoning for your placement of the events Weather problems and Fundingdelays.
Event Cost ($000) Probability Equipment breakdown Vendor is late with key segment Subcontractor has labor issues Weather problems Funding delays Testing delays 40 200 140 15 50 20 .20 .60 .30 Unknown .40 to.60 .40
Step by Step Solution
3.39 Rating (186 Votes )
There are 3 Steps involved in it
The weather problems 4 and funding delays 5 are placed using the highest probab... View full answer