Question: Given the time - phased work packages, complete the baseline budget form for the project. Chapter 8 Scheduling Resources and Costs 2 8 7 Activity

Given the time-phased work packages, complete the baseline budget form for the
project.
Chapter 8 Scheduling Resources and Costs 287
Activity 1
Task Budget
Activity 2
Activity 3
Activity 4
Activity 5
Total
Cumulative
4
6
10
8
3
31
4
132
2422
233
21
012345678910
Time-phased budget ($ 000)
Week
9.