Question: Given the time-phased work packages, complete the baseline budget form for theproject. Time-phased budget ($ 000) Week Task Budget o 1 2 3 4 5
-1.png)
Time-phased budget ($ 000) Week Task Budget o 1 2 3 4 5 6 7 8 9 10 Acivity 144 Activity 26 Activity 3 10 Activity 4 8 Activity 5 3 Total 31 Cumuiative