Question: Given the time - phased work packages, complete the baseline budget form for the project. table [ [ table [ [ Time -

Given the time-phased work packages, complete the baseline budget form for the project.
\table[[\table[[Time-phased budget ( $000)],[Week]]],[Task,Budget 0,,1,2,3,4,,5,6,7,8,9,10],[Activity 1,4,4,,,,,,,,",,,],[Activity 2,6,,1,3,,2,,,,,,,],[Activity 3,10,,2,4,,2,2,,,,,,],[Activity 4,8,,,,,,,2,3,3,,,],[Activity 5,3,,,,,,,,,,2,1,],[Total,31,,,,,,,,,,,,],[Cumulat,,,,,,,,,,,,,]]
 Given the time-phased work packages, complete the baseline budget form for