Question: Given the time-phased work packages and network, complete the baseline budget for the project. WP Design WP Survey WP Report 0 0 0 669

Given the time-phased work packages and network, complete the baseline budget for the project. WP Design WP Survey WP Report 0 0 0 669 13 Design 33 Cumulative 7 8 Task Budget Week 1 Week 2 Design 6 7 Survey Report Total 20 47 24 91 7 9 6 8 Project Network 32 7 Survey 6 Note: Leave no blanks for answers: enter 0 (the digit, not the letter) where necessary. 9 Week 3 Week 4 7 Time-phased budget ($ 000) Week 3 Week 5 Week 6 Week 7 Report 3 Week 8 Week 9 Week 10 Week 11 Week 12