Question: Given the two projects with given cash flows, the NPV of project A is how many more (or less) dollars than project B if the

Given the two projects with given cash flows, the NPV of project A is how many more (or less) dollars than project B if the discount rate is 9%?

Answer with two decimals.

Project A Project B

CF0: -13,773 -10,543

CF1: 3,480 1,723

CF2: 4,302 2,290

CF3: 9,768 4,794

CF4: 8,914 7,550

CF5: 2,684 12,530