Question: Given the unit data in Table , calculate the production cost for a 250-MW demand. Unit Capacity(MW) Forced Outage Rate $/MWh A 100 0.1 15
Given the unit data in Table , calculate the production cost for a 250-MW demand.
| Unit | Capacity(MW) | Forced Outage Rate | $/MWh |
| A | 100 | 0.1 | 15 |
| B | 150 | 0.2 | 25 |
| C | 200 | 0.25 | 40 |
| TIE | 1000 | 0 | 80 |
(1) Give the deterministic solution (no outages).
(2) Give the deterministic solution with unit derating.
(3) Give the probabilistic solution using state enumeration.
(4) Give the probabilistic solution using the convolution method