Question: Given the values for the critical path tasks below, compute the PERT E and SD for each task on scratch paper. What is the PERT

Given the values for the critical path tasks

Given the values for the critical path tasks below, compute the PERT E and SD for each task on scratch paper. What is the PERT E of the critical path? What is the PERT SD of the critical path? Task Optimistic Pessimistic PERTE PERT SD Most Likely 4 1 6 3 7 8 Load Data Analyze Data Report Findings 2 6 7 PERT E = 15.83 ; PERT SD = 1.44 PERT E = 15.83; PERT SD = 2.07 PERT E = 14.67 ; PERT SD = .83 PERT E = 14.67 ; PERT SD = .69 PERT E = 14.67 ; PERT SD = 2.49 PERT E = 15.83; PERT SD = .83