Question: Given this information: Daily demand = 50 units; Standard deviation of demand = 6 units; and lead time = 4 days. What is the reorder

Given this information: Daily demand = 50 units;
Given this information: Daily demand = 50 units; Standard deviation of demand = 6 units; and lead time = 4 days. What is the reorder point to attain a 5 percent risk of stock-out during lead time, assuming that the demand is distributed normally? 0 220 0 200 0 160