Question: Given this information: Daily demand = 50 units: Standard deviation of demand 6 units; and lead time = 4 days. What is the reorder point

Given this information: Daily demand = 50 units:
Given this information: Daily demand = 50 units: Standard deviation of demand 6 units; and lead time = 4 days. What is the reorder point to attain a 5 percent risk of stock-out during lead time, assuming that the demand is distributed normally? O 160 O 180 0 240 200 0 220