Question: [Graham] Graham, a general contractor, is trying to create a timetable of how long it will take his crew to transform one of his client's

 [Graham] Graham, a general contractor, is trying to create a timetable

[Graham] Graham, a general contractor, is trying to create a timetable of how long it will take his crew to transform one of his client's backyards. Below is a PERT diagram Graham created to help him determine how long will it take him to complete the job. Given the diagram below, what is the project's critical path and its duration? B) Remove old lower beds D) Plant The flowers A) Design the new r) complete job yard c) Upgrade me Build the pergola sprinkler system