Question: Great example Sacha! Yes, the network diagram gives you a visual of how you can save time and thus money. Class, Here is a challenge!
Great example Sacha! Yes, the network diagram gives you a visual of how you can save time and thus money.
Class,
Here is a challenge!
The term lag refers to the logical relationship between the start and finish of one activity and the start and finish of another. In practice, lags are sometimes incorporated into networks to allow for greater flexibility in network construction. Suppose we wished to expedite a schedule and determined that it was not necessary for a preceding task to be completely finished before starting its successor. We determine that once the first activity has been initiated, a two-day lag is all that is necessary before starting the next activity. Lags demonstrate this relationship between the tasks in question. They commonly occur under four logical relationships between tasks:
- Finish to Start
- Finish to Finish
- Start to Start
- Start to Finish
Also, let us take a look at the detail of an activity box:
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
