Question: GROUP ASSIGNMENT QUESTION ONE Fortune Global Shipping and logistics is a company located in Lagos Nigeria. The company desires to expand its logistics network and
GROUP ASSIGNMENT QUESTION ONE Fortune Global Shipping and logistics is a company located in Lagos Nigeria. The company desires to expand its logistics network and locate a facility within a network of three existing facilities. Given the following assumptions below, what are the coordinates for the new potential location? Assume the following, show the new location on the graph.
Warehouse 1 has a daily outbound goods volume of 2,500 units
Warehouse 2 has a daily outbound goods volume of 1,300 units
Warehouse 3 has a daily outbound goods volume of 5,000 units And the current coordinates of the existing facilities:
12
QUESTION TWO
a. Total quality management (TQM) means meeting the needs and expectations of customers, discuss. (5 marks)
b. State any 5 provisions of data protection Act of 1998
QUESTION THREE The information in the table below relates to an organization that is to undertake a project. Assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible: Task Description Duration (Working days) Predecessor/s A Requirement Analysis 5 - B Systems Design 15 A C Programming 25 B D Telecoms 15 B E Hardware Installation 30 B F Integration 10 C,D G System Testing 10 E, F H Training/Support 5 G I Handover and Go-Live 5 H a. Construct the network diagram and determine the critical path of the project b. Calculate the planned duration of the project in weeks c. Identify any non-critical tasks and the float (free slack) on each
| Task | Description | Duration (Working days) | Predecessor/s |
| A | Requirement Analysis | 5 | - |
| B | Systems Design | 15 | A |
| C | Programming | 25 | B |
| D | Telecoms | 15 | B |
| E | Hardware Installation | 30 | B |
| F | Integration | 10 | C,D |
| G | System Testing | 10 | E, F |
| H | Training/Support | 5 | G |
| I | Handover and Go-Live | 5 | H |
- Construct the network diagram and determine the critical path of the project
- Calculate the planned duration of the project in weeks
c. Identify any non-critical tasks and the float (free slack) on each