Question: h ) Draw AON diagram assuming a finish - start ( FS ) relationship between activities? ( 5 marks ) i ) You are tasked

h) Draw AON diagram assuming a finish-start (FS) relationship between activities? (5 marks)
i) You are tasked to draw using appropriate software an AOA PERT chart for the above project; assuming
a finish-start (FS) relationship between activities. (The length of the arrows must be indicative of the
duration).(10 marks)\table[[Activity,Duration,Predecessors],[A,2 days,-],[B,4 days,A],[C,10 days,B],[D,6 days,C],[E,8 days,Css2],[F,3 days,D,E
 h) Draw AON diagram assuming a finish-start (FS) relationship between activities?