Question: Hamid, a project manager, has a workload of 2 4 , 0 0 0 hours that needs to be completed in 7 5 workdays. He

Hamid, a project manager, has a workload of 24,000 hours that needs to be completed in 75 workdays. He has a team of 40 people who work for five 8-hour days per week. In those 75 days, 20 people have each requested three days off at different times. In this scenario, the workload is _____ of capacity
Question 25Answer
A.
95%
B.
75%
C.
80%
D.
102%
E.
150%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer