Question: hardware retail stores. Etoolie uses Fixed Order Quantity based EOQ as the lot sizing rule for its material requirements planning. BILL OF MATERIALS: FG: Assembled

hardware retail stores. Etoolie uses "Fixed Order Quantity" based EOQ as the lot sizing rule for
its material requirements planning.
BILL OF MATERIALS:
FG: Assembled by Etoolie - needs one SA1 and two SA2
SA1: Assembled by Etoolie - needs two P3(and other parts outside the scope of this exercise)
SA2: Assembled by Etoolie - needs three P3(and other parts outside the scope of this exercise)
P3: Part purchased by Etoolie from an overseas supplier
DEMAND:
COSTS:
Etoolie uses an inventory carrying charge of 15% per year for all its EOQ calculations.
ON-HAND INVENTORY BEFORE MONTH 1
a.(30 points) Generate the MRP output for items FG, SA1, SA2, and P3 using the above
information. Your answer should show for each item when its production should start or
when its purchase order should be placed with the supplier, as well as the associated
quantities.
b.(5 points) Ease of readability and verifiability of the spreadsheet developed for MRP
c.(5 points) What factors may require Etoolie to change the above MRP plan?
 hardware retail stores. Etoolie uses "Fixed Order Quantity" based EOQ as

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!