Question: hardware retail stores. Etoolie uses Fixed Order Quantity based EOQ as the lot sizing rule for its material requirements planning. BILL OF MATERIALS: FG: Assembled
hardware retail stores. Etoolie uses "Fixed Order Quantity" based EOQ as the lot sizing rule for
its material requirements planning.
BILL OF MATERIALS:
FG: Assembled by Etoolie needs one SA and two SA
SA: Assembled by Etoolie needs two Pand other parts outside the scope of this exercise
SA: Assembled by Etoolie needs three Pand other parts outside the scope of this exercise
P: Part purchased by Etoolie from an overseas supplier
DEMAND:
COSTS:
Etoolie uses an inventory carrying charge of per year for all its EOQ calculations.
ONHAND INVENTORY BEFORE MONTH
a points Generate the MRP output for items FG SA SA and P using the above
information. Your answer should show for each item when its production should start or
when its purchase order should be placed with the supplier, as well as the associated
quantities.
b points Ease of readability and verifiability of the spreadsheet developed for MRP
c points What factors may require Etoolie to change the above MRP plan?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock