Question: Harnesses are constructed in a process with two sequential resources. The capacities of the resources are 3.3 and 8.4 harnesses per minute Instruction: Round your

Harnesses are constructed in a process with two
Harnesses are constructed in a process with two sequential resources. The capacities of the resources are 3.3 and 8.4 harnesses per minute Instruction: Round your answer to three decimal places What is the capacity of this process in terms of harnesses per minute? harnesses per minute