Question: he correct sequence from longest to smallest duration scheduling is: Question 4 1 options: A ) A ) capacity planning, aggregate planning, master schedule, short
he correct sequence from longest to smallest duration scheduling is:
Question options:
A
A capacity planning, aggregate planning, master schedule, shortterm scheduling.
B
B aggregate planning, capacity planning, master schedule, shortterm scheduling.
C
C master schedule, capacity planning, aggregate planning, shortterm scheduling.
D
D master schedule, aggregate planning, capacity planning, shortterm scheduling