Question: If the highest priority is to minimize the average job lateness, then the jobs sequence should begin with those jobs requiring Question 3 2 options:
If the highest priority is to minimize the average job lateness, then the jobs sequence should begin with those jobs requiring
Question options:
A
The shortest processing time
B
The smallest critical ratio
C
The least remaining operations
D
The longest processing time
Question point
Which of the following is not a consideration when designing an appointment system?
Question options:
A
Determining the appointment time interval
B
Determining the appropriate sequencing rule
C
Determining the length of each workday and the time offduty
D
Deciding on an overbooking policy
Question point
Which of the following is NOT a key direct benefit from effective internal or external scheduling?
Question options:
A
A lower cost
B
B greater use of assets
C
C more dependable delivery
D
D higher quality
Question point
A work center had actual input of hours and actual output of hours. What is the change in backlog?
Question options:
A
A
B
B
C
C
D
D
Question point
Machine down time and downgrading costs are examples of which type of quality cost?
Question options:
A
Prevention
B
Appraisal
C
Internalfailure
D
Externalfailure
Question point
Which of the following is not one of W Edwards Deming's points?
Question options:
A
Stop making decisions purely on the basis of cost
B
Create a vision and demonstrate commitment
C
Eliminate exhortation
D
The only performance standard is Zero Defects
Question point
The shortterm scheduling activity called "loading":
Question options:
A
A assigns dates to specific jobs or operations steps.
B
B specifies the order in which jobs should be done at each center.
C
C assigns jobs to work centers
D
D assigns workers to jobs.
Question point
ISO : principles consist of all of the following except
Question options:
A
Involvement of people
B
Mutually beneficial supplier relationships
C
Zero defects
D
System approach to management
Question point
A manufacturing firm that produces a standardized product, not made of discrete parts, with littletono customization, with high demand, is most likely to use this type of process.
Question options:
A
project
B
job shop
C
flow shop
D
continuous flow
Question point
The correct sequence from longest to smallest duration scheduling is:
Question options:
A
A capacity planning, aggregate planning, master schedule, shortterm scheduling.
B
B aggregate planning, capacity planning, master schedule, shortterm scheduling.
C
C master schedule, capacity planning, aggregate planning, shortterm scheduling.
D
D master schedule, aggregate planning, capacity planning, shortterm scheduling.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock