Question: If the highest priority is to minimize the average job lateness, then the jobs sequence should begin with those jobs requiring Question 3 2 options:

If the highest priority is to minimize the average job lateness, then the jobs sequence should begin with those jobs requiring
Question 32 options:
A)
The shortest processing time
B)
The smallest critical ratio
C)
The least remaining operations
D)
The longest processing time
Question 33(1 point)
Which of the following is not a consideration when designing an appointment system?
Question 33 options:
A)
Determining the appointment time interval
B)
Determining the appropriate sequencing rule
C)
Determining the length of each workday and the time off-duty
D)
Deciding on an overbooking policy
Question 34(1 point)
Which of the following is NOT a key direct benefit from effective internal or external scheduling?
Question 34 options:
A)
A) lower cost
B)
B) greater use of assets
C)
C) more dependable delivery
D)
D) higher quality
Question 35(1 point)
A work center had actual input of 280 hours and actual output of 270 hours. What is the change in backlog?
Question 35 options:
A)
A)10
B)
B)-10
C)
C)0
D)
D)1.037
Question 36(1 point)
Machine down time and downgrading costs are examples of which type of quality cost?
Question 36 options:
A)
Prevention
B)
Appraisal
C)
Internal-failure
D)
External-failure
Question 37(1 point)
Which of the following is not one of W. Edwards Deming's 14 points?
Question 37 options:
A)
Stop making decisions purely on the basis of cost
B)
Create a vision and demonstrate commitment
C)
Eliminate exhortation
D)
The only performance standard is Zero Defects
Question 38(1 point)
The short-term scheduling activity called "loading":
Question 38 options:
A)
A) assigns dates to specific jobs or operations steps.
B)
B) specifies the order in which jobs should be done at each center.
C)
C) assigns jobs to work centers
D)
D) assigns workers to jobs.
Question 39(1 point)
ISO 9000:2000 principles consist of all of the following except
Question 39 options:
A)
Involvement of people
B)
Mutually beneficial supplier relationships
C)
Zero defects
D)
System approach to management
Question 40(1 point)
A manufacturing firm that produces a standardized product, not made of discrete parts, with little-to-no customization, with high demand, is most likely to use this type of process.
Question 40 options:
A)
project
B)
job shop
C)
flow shop
D)
continuous flow
Question 41(1 point)
The correct sequence from longest to smallest duration scheduling is:
Question 41 options:
A)
A) capacity planning, aggregate planning, master schedule, short-term scheduling.
B)
B) aggregate planning, capacity planning, master schedule, short-term scheduling.
C)
C) master schedule, capacity planning, aggregate planning, short-term scheduling.
D)
D) master schedule, aggregate planning, capacity planning, short-term scheduling.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!