Question: he differences between Top-down and Bottom-up budgeting approaches are a. Bottom-up budgeting is less accurate that top-down budgeting b. Top-down budgeting is more accurate that
he differences between Top-down and Bottom-up budgeting approaches are
a.
Bottom-up budgeting is less accurate that top-down budgeting
b.
Top-down budgeting is more accurate that bottom-up budgeting
c.
Top-down budgeting assumes that the project plans have been created, based on which the budget can be preliminarily estimated. Whereas bottom-up budgeting is a derivative of top-down, where detailed project plans are required
d.
Top-down budgeting assumes that since management is experienced with projects, they are therefore able to estimate project costs. Whereas bottom-up budgeting is based on the project plans as the first step