Question: he Fresh Connection is looking at the needs for a new processing operation. The demand at this operation is 3 1 5 units per day.

he Fresh Connection is looking at the needs for a new processing operation. The demand at this operation is 315 units per day. Given the combination of regular time, overtime and some additional time available due to cross training, this operation is up and running for 18.2 hours per day across multiple shifts.
Task Time Req. (min.) Predecessor Tasks
a 10.73-
b 6.83 a
c 9.25 b
d 12.17 c
e 14.08 d
f 5.82 e
g 7.99 f
h 13.63 g
Assuming that each task must be completed in sequence and that each task has its own workstation, what is the efficiency of the line (stated as a percent)?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!