Question: The Fresh Connection is looking at the needs for a new processing operation. The demand at this operation is 1 8 3 units per day.

The Fresh Connection is looking at the needs for a new processing operation. The demand at this operation is 183 units per day. Given the combination of regular time, overtime and some additional time available due to cross training, this operation is up and running for 22.8 hours per day across multiple shifts.
Task Time Req. (min.) Predecessor Tasks
a 12.08-
b 12.32 a
c 12.93 b
d 9.83 c
e 12.87 d
f 6.44 e
g 13.92 f
h 9.15 g
Assuming that each task must be completed in sequence and that each task has its own workstation, what is the cycle time?