Question: he project manager has identified four tasks that can be distributed among the 4 program directors. The time taken to complete the four tasks is

he project manager has identified four tasks that can be distributed among the 4 program directors. The time taken to complete the four tasks is given below,Time taken for completing the task PROGRAM DIRECTOR A B C D TASK 125304041 TASK 233363441 TASK 342434539 TASK 439384042How many allocations are possible?
a.
24
b.
4
c.
8
d.
16

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!