Question: he second step in the project control process for measuring and evaluating project performance is to Question 3 5 options: review the baseline plan with
he second step in the project control process for measuring and evaluating project performance is to
Question options:
review the baseline plan with top management
analyze inputs to control system
compare plan against actual
measure progress and performance
review spending with team members