Question: Question 4 (Mandatory) (1 point) The third step in the project control process for measuring and evaluating project performance is to analyze inputs to
Question 4 (Mandatory) (1 point) The third step in the project control process for measuring and evaluating project performance is to analyze inputs to the control system. review spending with team members. Oreview the baseline plan with top management. compare the plan against actual performance. measure both progress and performance. Question 5 (Mandatory) (1 point) The final step in the project control process for measuring and evaluating project performance is to follow up on corrective action. take appropriate action. prepare a report to top management. review spending with team members. measure progress and performance. Question 6 (Mandatory) (1 point) A_ project. Gantt chart is a simple and effective way to depict progress on a baseline tracking control variance simple