Question: Hello can you answer asap and I will rate a thumbs up? 1) The time required to complete a group of jobs is referred to
Hello can you answer asap and I will rate a thumbs up?
1) The time required to complete a group of jobs is referred to as
Select one:
a. completion time
b. makespan
c. flow time
d. None of these answer choices is correct
2)
The process of prioritizing jobs that have been assigned to a resource is called
Select one:
a. loading
b. monitoring
c. sequencing
d. input/output analysis
3)
If a job is ahead of schedule, then its critical ratio (CR) will be
Select one:
a. less than one
b. None of these answer choices is correct
c. equal to one
d. greater than one