Question: Hello, can you assist PLEASE? Multiple Choice (Practice Questions) 43. How would you describe the process capability index? A. The ability of a process to

Hello, can you assist PLEASE?

Multiple Choice (Practice Questions)

43. How would you describe the process capability index?

A. The ability of a process to convert inputs into outputs

B. The capability within a process a process to convert inputs into outputs

C. The statistical ratio and proven capability of a process to produce outputs within specifications limits

D. To be capable of producing project deliverable results within a zero-cost defect

E. None of these are correct

44. Obligations to satisfy the planned project outputs as scheduled?

A. Starts with the project start-up meeting

B. Is ensured by the process measurements applied

C. Is provided by the project quality plan

D. is confirmed in the project tender document

E. The approved internal auditing program

45. How does the project manager conform to the standard set by the quality manager

A. Manage the planning in complaint with the plan quality requirements

B. Manage the quality in conformance with planned quality requirements

C. Control the planned quality requirements in compliance scope requirements

D. All of the above

E. None of the above

46. What are the same general tasks that a project manager and general manager performs?

A. they plan, schedule, motivate and control the task

B. they manage recruitment and appoint teams

C. they manage procurement and production tasks

D. they manage financial and marketing tasks

E. they scrutinize schedule and all tasks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!