Question: Hello! Can you please help me with this summary? Can you offer key points that need to be addressed? Thanks! Ventura Baseball Stadium is a

Hello! Can you please help me with this summary? Can you offer key points that need to be addressed? Thanks!

Ventura Baseball Stadium is a 47,000-seat professional baseball stadium. G&E Company began construction on June 10, 2019, and plans to complete it on February 21, 2022. The stadium must be ready for the opening of the 2022 regular season. G&E would accrue a $500,000 per-day penalty for notmeeting the April 3, 2022, deadline.

The project started on time and was progressing well until an accident occurred during the pouring of the lower bowl. Two workers were seriously injured, and the activity was delayed four weeks while the cause of the accident was investigated and the site cleared to proceed.

The president of G&E Company, Percival Young, is concerned about the delay of the project.

The project began with roughly six weeks of cushion between expected completion deadline and imposed deadline of April 3 (opening day). Now there is only a two-week cushion with over a year's worth of work still to be completed. He has asked you to consider the following options to reduce theduration of the project and restore some of the time buffer that has been lost.

A. Assign overtime to complete the installation of seats in 120 days, not 140 days.

B. Assign overtime to complete the infrastructure in 100 days, not 120 days.

C. Introduce a start-to-start lag whereby construction of the roof begins 70 days after the start of buildingroof supports.

D. Introduce a start-to-start lag whereby installing the scoreboard can start 100 days after the start ofconstruction of the upper steel bowl.

E. Introduce a start-to-start lag whereby installing seats can start 100 days after the start of both pouringthe main concourse and constructing the upper steel bowl.

Can you please help me with key points that I need to highlight when I compile my report?

Hello! Can you please help me with this summary? Can you offerkey points that need to be addressed? Thanks!Ventura Baseball Stadium is a

\fActivity list Duration Start finish Predecessors Baseball Stadium ID Activity Duration Predecessors 1 Stadium Project 2 Clear stadium site 60 day's 2 Clear stadium site 60 Demolish building 30 days 2 Set up construction site 30 days 3 3| Demolish building 30 Drive support piling 120 days Pour lower concrete bowl 120 days 4 Set up construction site 30 17 Pour main concourse 120 days 4.6 8 Install playing field 90 days 4, 6 5 Drive support piling 120 9 Construct upper steel bowl 120 days 4,6 Pour lower concrete bowl 10 7.9 120 Install seats 140 days 11 Build luxury boxes 90 days 7.9 | Pour main concourse 120 4, 6 12 Install jumbotron 30 days 7. 9 13 Stadium infrastructure 120 days 7.9 81 Install playing field 90 4,6 14 Construct steel canopy 75 days 10 15 Light installation 30 days 14 9 Construct upper steel bowl 120 4, 6 16 Build real supports 90 days 6 17 Construct roof 180 day's 16 Install seats 140 7.9 18 Install roof tracks 90 days 16 1 Build luxury boxes 7,9 19 Install roof 90 days 17, 18 90 20 Inspection 20 days 8, 11. 12, 13. 15, 19 21 Install jumbotron 30 7,9 3 Stadium infrastructure 120 7,9 For purposes of this case assume the following. 141 Construct steel canopy 75 10 1. The following holidays are observed: January 1. Martin Luther King Day (third 15 Light installation 30 Monday in January), Memorial Day (last Monday in May). July 4th, Labor Day 161 Build roof supports 90 (first Monday in September). Thanksgiving Day (fourth Thursday in November), 17 Construct roof 180 16 December 25 and 26. 18\\ Install rooftracks 90 16 2. If a holiday falls on a Saturday, Friday will be given as an extra day off, and if it 191 Install roof 90 17 18 falls on a Sunday, Monday will be given as a day off. 20 Inspecton 20 8, 11, 13, 15, 19 3. The construction crew works Monday through Friday

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!