Question: Hello, I am having trouble setting up this part for the binary constraints using solver in excel. Please help! Due to scheduling conflicts, R&D has

Hello, I am having trouble setting up this part for the binary constraints using solver in excel. Please help!

Due to scheduling conflicts, R&D has determined that at most, one of projects 1 and 2 should be pursued. Additionally, if project 2 is chosen, project 4 must also be chosen.